Permitting process has begun
Posted on: June 16, 2016 - 9:22am
Permitting for the Phase One treatment plant on the Town-owned site has begun. The Planning Coordinator submitted an Environmental Notification Form (ENF) in May to the Massachusetts Environmental Protection Agency (MEPA). On June 8 a MEPA staff member walked the site with members of the Committee. A ruling is expected by the end of June.